Saturday, February 11, 2012

JOKE: BILLY BOB AND THE MADAM

In a small town in Tennessee, Big Bubba decides it's time for his son, 14-year-old Billy Bob, to learn the facts of life.
He takes him to the local house of ill repute, which is fronted by a beauty parlor.

Bubba introduces Billy Bob to the madam, and explains that it's time for his indoctrination to sex.
The madam says, "Bubba you've been such a good customer over the years, I'm going to see to this personally."

So the madam takes Billy Bob by the hand and leads him upstairs, where she completes his deflowering.
Later, as they are walking downstairs the madam says, "Since this is your first time, I'm going to see that you get the full treatment before you leave. I'm going to give you a manicure."

Two weeks later Bubba and Billy Bob run into the madam on the main street.
Billy Bob is acting a little shy. So the madam smiles and says, "Well, Billy Bob, don't you remember me?"

"Yes, Ma'am, the boy stammers, "you're the lady that give me the crabs and then cut off my fingernails so I couldn't scratch 'em."

VIDEO: Now THIS is a Crane..One Crane Lifting a 10 Story Steel Block



12,481 employees, 64 wheel powered hydraulic jack transporters, 1000 foot floating drydocks plus assorted gantry and tower cranes are some of the most important tools being used by Samsung Heavy Industries Shipyard to build vessels that cost up to $5 billion each! But the most impressive industrial behemoth they own is undoubtedly the 3000 ton double boom sheerleg floating crane used to transport mega-blocks.

What’s a megablock? Well, first a little background on how the world’s largest ships are constructed…

A mega block is one of a set of large components, assembled from bow to stern, that make up a ship. Samsung builds the blocks one sheet of steel at a time through the process of cutting, and welding steel plates together. Once assembled on large concrete parking lots surrounding the shipyard, each block is fitted with pipes, electric cabling, ventilation and the parts required inside the ship’s hull.

At this time the ship is essentially built, but exists in up to 2 dozen separate pieces that need are fitted together like an big-block Lego set. Moving these blocks from land to sea requires hydraulic jack transporters with 64 wheels which scoot under the megablocks and enough hydraulic power to lift thousands of tons. But the blocks still need to be set inside the dry-docks, which will be filled with water to float the ship.

Historically a crane could only carry up to 500 tons to the docks, meaning that smaller blocks would be constructed on land leaving gantry cranes the job of going back and forth in to move countless blocks to the docks to build a single ship. But megablocks, 3,000-ton large blocks at a size that was 5-6 times larger than the previously-used blocks, are more efficient – fewer need to be built for each ship.

To accommodate these mega-blocks Samsung purchased huge machines mounted on enormous barges. Called double boom sheerleg floating cranes, these jumbo-cranes are among the largest and most powerful in the world capable of lifting up to 3,000 tons of steel.

In the past 90 blocks were required to build a large oil tanker, but by using mega-block technology coupled with sheerleg cranes, only ten megablocks are needed. This has shortened the ship construction period within the drydock from three months to 1.5 months and allows to Samsung to have the highest dock-turnover time in the world. By maximizing technology and utilizing new crane design SHI was able to maximize production volume and reach a record of just over one mega-ship launch per week!

As for the crane that does the lifting. crane has 8 main hooks, each with a 1000T capacity at an 82 meters boom heel.  The entire structure is supported on a steel barge that’s maneuvered with the help of powerful tug boats and set in place – with only millimeters of tolerance – by massive anchors spread out like spider-webs from the hull of the barge.

Some operations, however, are too large and complicated for the human brain to comprehend by words alone. For those times when we need to understand the seemingly impossible, video is the only way to go. The following is video of a mega sheerleg crane in action setting a 10 story steel accommodations megablock on top of a brand new $750 million dollar, 750 ft long, 137 ft deep offshore drillship. The video was taken using time-lapse photography but the overall operation – from lifting the megabuck from land to setting it precisely (within millimeters of accuracy) in place – takes only about 6 hours to complete. Take a look:

VIDEO: Dog Wears Milk Pants to Feed Baby Goats

VIDEO: No Fear in the Now..97 Seconds that May Change Your Life..

VIDEO: FIRST PARAPLEGIC BACK FLIP ON SKIS

How rad is Josh Dueck? 8 years ago Josh suffered a broken T11 which made him fully paraplegic from the waist down during a skiing accident.
For the past 8 years Josh has wanted to get inverted again above snow and on Feb. 3rd 2012 Josh landed the first Sit Ski Back Flip ever! Congrats Josh!!

VIDEO: Donkey Fan

digitalpoint

Geo Visitors Map

~WHIRLED GNUS~

Followers

Blog Archive